China PVC market pick up as local supply curtails following another explosionChina PVC market pick up as local supply curtails following another explosion |
|
Serangkaian ledakan di pabrik kimia mendorong pemerintah China memperketat inspeksi keselamatan pada beberapa pabrik di China Utara sejak Maret. Karena itu banyak pabrik menurunkan tingkat operasi termasuk yang dalam bisnis carbide.
Ledakan di Xinjiang Yihua Chemical Group awal bulan ini mengganggu pasokan carbide, memaksa produsen PVC carbide mempertahankan harga untuk mendapat keuntungan.
Masalah memburuk, dini hari 24 April 2019 ledakan terjadi lagi di Mongolia Dalam Yidong Dongxing Chemical Co Ltd, membuat perusahaan menghentikan pabrik PVC 300,000 ton/tahun carbide based tanpa batas waktu.
Dilaporkan sebagian besar pemasok lokal segera menarik penawaran spot setelah insiden karena inspeksi keselamatan yang semakin ketat akan dilkeluarkan, mungkin mempersulit pasokan lebih lanjut.
Beberapa pembeli China mencari kargo Asia Tenggara untuk menghindari bea antidumping dan dilaporkan penawaran kargo Thailand mencapai $ 870/ton CFR China minggu ini.
Produsen Taiwan menaikkan penawaran sebesar $ 15-30/ton dari minggu lalu, membuat harga baru menjadi $ 840/ton CFR China. Sumber menambahkan, "pasar yakin pola harga-harga mulai rebound dari dasar. Kami berharap lebih banyak penjual impor menaikkan penawaran beberapa hari mendatang. "
Kekurangan pasokan persediaan stok diperkirakan akan memburuk dalam waktu dekat karena jadwal penutupan pemeliharaan besar pada pabrik-pabrik utama di China. CommoPlast menggabungkan dan melaporkan detail shutdown ini pada tabel berikut:
Plant Name |
Type |
Capacity |
Details |
Qinghai Salt Lake |
Carbide |
200,000 |
Unexpected shutdown since 13 Feb |
Hebei Shenghua |
Carbide |
260,000 |
Unexpected shutdown since 28 Nov 2018 |
Wuhu Ronghui |
Carbide |
50,000 |
12 March to H2 April |
Yunnan Nan Lin |
Carbide |
330,000 |
1 April to unknown |
Suzhou Huasu |
Ethylene |
130,000 |
8 April to 20 April |
Hubei Yihua |
Carbide |
250,000 |
12 April, 7-10 days |
Xiyang Chemical |
Carbide |
100,000 |
12 April to unknown |
Wuhai Chemical |
Carbide |
300,000 |
15 April, 10 days |
Jiyuan Fangsheng |
Carbide |
50,000 |
21 April, 4-5 days |
Xinjiang Yili Nangang |
Carbide |
120,000 |
22 April, 15 days |
Inner Mongolia Yidong Chemical |
Carbide |
300,000 |
24 April explosion |
Qinghai Yihua |
Carbide |
300,000 |
April, 5 days |
Xinjiang Tianye |
Carbide |
1,300,000 |
Mid of May |
Xinjiang Zhongtai (Midong) |
Carbide |
800,000 |
Mid of May, 7 days |
Shanxi Yushe Chemical |
Carbide |
300,000 |
15 May, 3 days |
Shaanxi Jintai |
Carbide |
300,000 |
15 May, 15-20 days |
Ordos |
Carbide |
400,000 |
Mid of May |
Shanxi Ruiheng (Phase I) |
Carbide |
200,000 |
Mid of May |
Shaanxi Beiyuan |
Carbide |
1,100,000 |
May |
Inner Mongolia Dongxing |
Carbide |
360,000 |
May |
Henan Shenma |
Carbide |
300,000 |
May |
Sichuan Jinlu |
Carbide |
240,000 |
May |
Lu Tai Chemical |
Carbide |
360,000 |
end of May |
Yangmei Hengtong |
Ethylene |
300,000 |
May, 20 days |
Dezhou Shihua |
Carbide |
400,000 |
H2 May |
Jilantai |
Carbide |
400,000 |
end of June |
Heilongjiang Yuhua |
Carbide |
300,000 |
end of June |
Shanxi Yangmei Hengtong |
Carbide |
300,000 |
May, 20 days |
Inner Mongolia Yili Chemical |
Carbide |
500,000 |
May, 7-10 days |
Yangmei Xiyang Chemical |
Carbide |
100,000 |
May |
Zhonggu Mining |
Carbide |
300,000 |
May |
Tianjin Dagu |
Ethylene |
800,000 |
May, 3 weeks |
Country
China