PetroRabigh to restart operations after maintenance shutdown
PetroRabigh to restart operations after maintenance shutdown

CommoPlast 02.12.2015
According to a media report, PetroRabigh will restart operations at part of its refining and petrochemical complex on Thursday after a 50-day planned maintenance shutdown since Oct 2015.
In a statement on Tuesday, the company said that its olefin cracker unit and subordinate units would remain offline for further maintenance work, which is expected to last until 30 Dec.
Beside the refinery complex, PetroRabigh houses a petrochemical complex on the same area to produce the following signify products:
Product |
Capacity |
Ethylene |
1.3 million tons/y |
Propylene |
900,000 tons/y |
HDPE |
300,000 tons/y |
LLDPE |
600,000 tons/y |
PP |
700,000 tons/y |