11 Nov 2020
Downstream units at the same site are integrated with the cracker, however, these units have yet to come online.
10 Nov 2020
The company decided to keep several downstream units operating due to healthy demand.
06 Nov 2020
The producer has not disclosed the timeline to when the unit could resume normal operating rates.
The unit is expected to remain offline until the end of November.
05 Nov 2020
The fire broke out during the early hours of 5 November 2020 that forced the company to shut its naphtha cracker on the site.
30 Oct 2020
According to market sources, Shaanxi Yanchang Zhongmei Yulin Phase II has successfully conducted trial production for its ...
28 Oct 2020
The company kickstarted the project in early 2018 as part of PTTGC’s $4.5 billion project to “retrofit” its Map Ta Phut site.