05 Jan 2021
The restart of ENEOS Corp’s cracker come together with three other major crackers in South Korea, which expected to ease the ethylene supply tightness in the region.
The shutdown is expected to curtail local supply further and continue to lift spot prices in this market in the near term.
04 Jan 2021
The restarts are expected to boost the availability of both ethylene and propylene monomers within the region.
30 Dec 2020
The restart schedule could not be ascertained at the time of this report.
29 Dec 2020
The company informed that it is planning to also shut the No. 1 and No. 2 olefins plants at the same location in the first quarter of 2021.
22 Dec 2020
SCG took these units offline in November 2020 for 45-days maintenance.
The company took the cracker off-stream around the third week of October 2020 for two months of maintenance and expanding the capacity.